October 30, 2026
The Local Echo

Local news from public records, city by city

TransportBurnaby

Paving work on Delta Avenue between Northlawn and Fairlawn drives, October 29 to November 5

Traffic control is in place on Delta Avenue for paving after earlier fortis work. The road stays open, and the street is on a bus route.

Paving work started October 29 on Delta Avenue between Northlawn Drive and Fairlawn Drive and is scheduled to run to November 5. The paving follows earlier fortis work on the street.

Crews are working daily from 0900 to 1500 under traffic control permit TC26-01616, which is approved. The road is not fully closed. The City lists the street as a bus route, with 2 business days of additional bus-route requirements, and says parking service is needed, with 5 business days of additional requirements. No noise variance is required.

Facebook X WhatsApp Email

Sources

  • Concrete/asphalt/milling/paving work traffic control on Delta Avenue between Northlawn Drive and Fairlawn Drive (TC26-01616)

This story was checked against the sources above before publishing. Editorial policy · Report an error